Shree Cement share news and announcements
NSE: SHREECEMBSE: 500387Cement & Cement ProductsMid Cap
Share price at the NSE close on 23 Oct 2026. Previous close ₹22,330.00.
- Next results date: the board meets on 23 Oct 2026 to consider: financial results.
- Market capMarket capitalisation. Share price times the number of shares: what the whole company is worth at the day's price. The rank is by average market value over the six months to Jun 2026, among listed companies.
- ₹82,030 Cr120th largest listed
- P/EPrice to earnings, trailing. Market cap divided by the profit of the last twelve months (the latest four quarters, or two half years for a company that reports half-yearly) that belongs to the company's own shareholders, after the share of the other owners of its subsidiaries: what investors pay for each rupee of a year's profit. The filing of 31 Jul 2026
- 50.3
- P/BPrice to book. Market cap divided by the net worth that belongs to the company's own shareholders, its assets less everything it owes and less the other owners' share of its subsidiaries, on its latest balance sheet. The filing of 6 May 2026
- 3.5
- Dividend yieldDividend yield. Dividends paid per share in the twelve months to the day, as a percentage of the day's share price.
- 0.66%
- ROEReturn on equity. Profit over the last twelve months (the latest four quarters, or two half years for a company that reports half-yearly) that belongs to the company's own shareholders, as a percentage of their net worth, the money they have in the business. Net worth is the average of the latest balance sheet and the one a year before it. The filing of 31 Jul 2026
- 7.3%
- ROCEReturn on capital employed. Operating profit after depreciation (revenue less operating expenses and depreciation, without other income and one-off items) as a percentage of all the money the business runs on: the whole group's net worth, the other owners of its subsidiaries included, plus borrowings. Lease liabilities are not counted: the results filings do not state them. The profit is over the last twelve months (the latest four quarters, or two half years for a company that reports half-yearly); net worth and borrowings are on the latest balance sheet. The filing of 31 Jul 2026
- 7.0%
- Debt to equityDebt to equity. Borrowings divided by the whole group's net worth, the other owners of its subsidiaries included: rupees borrowed for each rupee of equity in the business. Lease liabilities are not counted: the results filings do not state them. From the balance sheet at the end of Mar 2026.
- 0.07
- Volume, NSEVolume. Shares traded on the last trading day; delivery is the part buyers kept rather than sold again the same day.
- 60,77723.5% delivered
Shree Cement share news and announcements
866 announcements, routine notices left out, newest first. Page 17 of 18.
Oct 2009
1 Oct · Board meeting
To consider and approve, inter-alia, the Unaudited Financial Results for the second quarter and Half year ended on September 30, 2009.
Sep 2009
30 Sep · Disclosure
Mr. Prashant Bangur, Executive Jt. President of the Company has purchased 1755 Equity Shares of the Company on September 25, 2009. The transaction was through Stock Exchange. Further, the details of the Shareholding of Mr. Prashant Bangur before and after the above transactions shall be available on the NSE website (http://www.nseindia.com) under: Corporates > Latest Announcements and on the Extranet Server (/Common/Corporate Announcements). For more details click here.25 Sep · Disclosure
Mr. M.K. Singhi, Executive Director of the Company has sold 500 Equity Shares of the Company on September 18, 2009 and September 22, 2009. The transaction were through Stock Exchange. Further, the details of the Shareholding of Mr. M.K. Singhi before and after the above transactions shall be available on the NSE website (http://www.nseindia.com) under: Corporates > Latest Announcements and on the Extranet Server (/Common/Corporate Announcements). For more details click here.
Aug 2009
17 Aug · Meeting
Shree Cements Ltd. has submitted to the Exchange a copy of the proceedings of the Annual General Meeting of the Company held on July 24, 2009. A copy of the same shall be available on the NSE website (http://www.nseindia.com) under: Corporates > Latest Announcements and on the Extranet Server (/Common/Corporate Announcements). For more details click here.
Jul 2009
24 Jul · Results
Standalone Results for the quarter ended on 30-JUN-2009 as follows: Net Sales of Rs. 92244.67 lacs for quarter ending on 30-JUN-2009 against Rs. 61432.49 lacs for the quarter ending on 30-JUN-2008. Net Profit / (Loss) of Rs. 29113.27 lacs for the quarter ending on 30-JUN-2009 against Rs. 11090 lacs for the quarter ending on 30-JUN-2008.16 Jul · Meeting
Notice of the Annual General Meeting of the Shareholders of the Company to be held on July 24, 2009. A copy of the same shall be available on the NSE website (http://www.nseindia.com) under: Corporates > Latest Announcements and on the Extranet Server (/Common/Corporate Announcements). For more details click here.7 Jul · Board meeting
Considering and approving inter-alia, the unaudited financial results of the Company for the quarter ended June 30, 2009.
May 2009
8 May · Meeting
Register of Members and Share Transfer Books of the Company shall remain close from July 20, 2009 to July 24, 2009 (both days inclusive) for the purpose of Annual General Meeting scheduled to be held on July 24, 2009 and declaration of dividend.
Apr 2009
28 Apr · Results
Standalone Results for the quarter ended on 31-MAR-2009 as follows: Net Sales of Rs. 80620.29 lacs for quarter ending on 31-MAR-2009 against Rs. 65007.12 lacs for the quarter ending on 31-MAR-2008. Net Profit / (Loss) of Rs. 23563.65 lacs for the quarter ending on 31-MAR-2009 against Rs. 4107.54 lacs for the quarter ending on 31-MAR-2008.28 Apr · Results
Standalone Results for the year ended on 31-MAR-2009 as follows: Net Sales of Rs. 271502.02 lacs for year ending on 31-MAR-2009 against Rs. 206586.8 lacs for the year ending on 31-MAR-2008. Net Profit / (Loss) of Rs. 57796.94 lacs for the year ending on 31-MAR-2009 against Rs. 26037.2 lacs for the year ending on 31-MAR-2008.28 Apr · Dividend
Board, at its meeting held on April 28, 2009 has declared Interim Dividend @ Rs.5 per share and also recommend to members of the Company final dividend @ Rs.5 per share for the financial year 2008-09.
Mar 2009
30 Mar · Corporate action
Shree Cements Ltd had informed the Exchange regarding Board Meeting to be held on April 13, 2009 to consider and approve, interalia the payment of Interterm Dividend to Equity Shareholders of the Company, whose name appear in the Register of Member on Record Date. Further the Company had fixed April 18, 2009 as the Record Date for the payment of interim Dividend, if declared by the Board in the meeting. The date of payment of Interim Dividend shall be on or after April 18, 2009. The Company has now informed the Exchange that the Record Date for the purpose of payment of Interim Dividend has been rescheduled as May 05, 2009 and consequently the date of payment of interim dividend has also be rescheduled as May 05, 2009 onwards.30 Mar · Board meeting
Company had informed the Exchange regarding Board meeting to be held on April 13, 2009 to consider and approve, interalia the payment of Interterm Dividend to Equity Shareholders of the Company. The Company has now informed the Exchange that the meeting of the Board of Directors of the Company has been rescheduled for April 28, 2009 to consider and approve the un-audited financial results for the quarter and year ended March 31, 2009 and the payment of interim dividend to Equity Shareholders of the Company.(Purpose Revised)26 Mar · Board meeting
To consider and approve, interalia the payment of Interterm Dividend to Equity Shareholders of the Company, whose name appear in the Register of Member on Record Date. Further the Company has fixed April 18, 2009 as the Record Date for the payment of interim Dividend , if declared by the Board in the meeting. The date of payment of Interim Dividend shall be on or after April 18, 2009.25 Mar · Updates
Company on March 24, 2009 has commissioned its Clinker Manufacturing Unit (Unit VII) of 1 Million tonnes Per Annum capacity at Bangur City, Ras in Pali Distt of Rajasthan. Company has set a world record by commissioning this unit in a period of 367 days (12 months) against the industry standard of 630 days (21 months).
Jan 2009
28 Jan · Results
Standalone Results for the quarter ended on 31-DEC-2008 as follows: Net Sales of Rs. 66530.96 lacs for quarter ending on 31-DEC-2008 against Rs. 52357.27 lacs for the quarter ending on 31-DEC-2007. Net Profit / (Loss) of Rs. 12394.02 lacs for the quarter ending on 31-DEC-2008 against Rs. 3503.45 lacs for the quarter ending on 31-DEC-2007.
Dec 2008
31 Dec · Board meeting
To consider and approve, inter-alia, the Unaudited Financial Results for the Quarter and nine months ended on December 31, 2008.
Oct 2008
20 Oct · Results
Standalone Results for the half year ended on 30-SEP-2008 as follows: Net Sales of Rs. 124350.77 lacs for half year ending on 30-SEP-2008 against Rs. 89222.41 lacs for the half year ending on 30-SEP-2007. Net Profit / (Loss) of Rs. 21839.27 lacs for the half year ending on 30-SEP-2008 against Rs. 22314.67 lacs for the half year ending on 30-SEP-2007.20 Oct · Results
Standalone Results for the quarter ended on 30-SEP-2008 as follows: Net Sales of Rs. 62918.28 lacs for quarter ending on 30-SEP-2008 against Rs. 46638.99 lacs for the quarter ending on 30-SEP-2007. Net Profit / (Loss) of Rs. 10749.27 lacs for the quarter ending on 30-SEP-2008 against Rs. 10623.35 lacs for the quarter ending on 30-SEP-2007.7 Oct · Updates
Shree Cements Ltd had informed the Exchange that Company has commissioned its 18 MW Turbine Generator Set (TG - VII) on 27.9.08. The TG Set has been setup at Bangur City, Ras, District Pali, Rajasthan. The Company has now informed the Exchange that the "TG-VI" has been inadvertently mentioned as "TG-VII".6 Oct · Board meeting
To consider and approve, inter-alia, the Unaudited Financial Results for the Second quarter and Half Year ended on September 30, 2008.
Sep 2008
29 Sep · Updates
Company has commissioned its 18 MW Turbine Generator Set (TG - VII) on 27.9.08. The TG Set has been setup at Bangur City, Ras, District Pali, Rajasthan
Aug 2008
22 Aug · Meeting
Proceedings of Annual General Meeting of the Company held on July 18, 2008. A copy of the same shall be available on the NSE website (http://www.nseindia.com) under: Corporates > Latest Announcements and on the Extranet Server (/Common/Corporate Announcements). For more details click here.
Jul 2008
18 Jul · Results
Standalone Results for the quarter ended on 30-JUN-2008 as follows: Net Sales of Rs. 61432.49 lacs for quarter ending on 30-JUN-2008 against Rs. 42583.42 lacs for the quarter ending on 30-JUN-2007. Net Profit / (Loss) of Rs. 11090 lacs for the quarter ending on 30-JUN-2008 against Rs. 11691.32 lacs for the quarter ending on 30-JUN-2007.
Jun 2008
23 Jun · Board meeting
Meeting on 18 Jul 2008: “Unaudited Financial Results for the Qtr ended June 30, 2008”4 Jun · Meeting
Register of Members and Share Transfer Books of the Company shall remain close from July 14, 2008 to July 18, 2008 (both days inclusive) for the purpose of Annual General Meeting scheduled to be held on July 18, 2008 and declaration of dividend.
May 2008
7 May · Results
Standalone Results for the quarter ended on 31-MAR-2008 as follows: Net Sales of Rs. 66007.12 lacs for quarter ending on 31-MAR-2008 against Rs. 37827.08 lacs for the quarter ending on 31-MAR-2007. Net Profit / (Loss) of Rs. 4107.54 lacs for the quarter ending on 31-MAR-2008 against Rs. 2389.45 lacs for the quarter ending on 31-MAR-2007.7 May · Dividend
Board has decided in the meeting held on May 07, 2008 to recommend members of the Company payment of dividend @ Rs.8.00 per share for the year 2007-08.7 May · Results
Standalone Results for the year ended on 31-MAR-2008 as follows: Net Sales of Rs. 206586.8 lacs for year ending on 31-MAR-2008 against Rs. 136797.52 lacs for the year ending on 31-MAR-2007. Net Profit / (Loss) of Rs. 26037.2 lacs for the year ending on 31-MAR-2008 against Rs. 17700.23 lacs for the year ending on 31-MAR-2007.
Apr 2008
23 Apr · Board meeting
To consider and approve, inter-alia, the Audited Annual Accounts for the year ended March 31, 2008.
Mar 2008
24 Mar · Updates
The Company has commissioned its 18 MW Captive Thermal Power Plant (CPP-V) at Bangur City, Ras, District Pali, Rajasthan on 23 March, 200824 Mar · Updates
The Company has commissioned its Unit - VI of 1.0 MTPA clinker production capacity at Bangur City, Ras, District Pali, Rajasthan on 23rd March, 2008
Feb 2008
20 Feb · Legal
Vide its letter dated February 20, 2008 giving clarification on the News Article regarding Investment in Cement Plant in M.P. In this regard Company has clarified as follows: "Board of Directors of the Company has not taken up any such investment decision for setting up the cement project in M.P. Company has not even secured the limestone mines for the above project, although, it is making necessary efforts in this direction. There is no concrete plan for such investment duly approved by Board as of today. The new item has been printed without anybody's knowledge in the Company and hence the media report should not be relied upon".
Jan 2008
8 Jan · Results
Standalone Results for the quarter ended on 31-DEC-2007 as follows: Net Sales of Rs. 52357.27 lacs for quarter ending on 31-DEC-2007 against Rs. 36453.79 lacs for the quarter ending on 31-DEC-2006. Net Profit / (Loss) of Rs. 3503.45 lacs for the quarter ending on 31-DEC-2007 against Rs. 10412.9 lacs for the quarter ending on 31-DEC-2006.
Dec 2007
28 Dec · Board meeting
To consider and approve, inter-alia, the Unaudited Financial Results for the Third Quarter and Nine Months ended on December 31, 2007.27 Dec · Updates
The Company has commissioned its second 1.5 MTPA Cement Grinding Unit at Village Khushkhera, near Gurgaon on 26th December, 2007
Oct 2007
23 Oct · Results
Standalone Results for the half year ended on 30-SEP-2007 as follows: Net Sales of Rs. 89222.41 lacs for half year ending on 30-SEP-2007 against Rs. 62534.45 lacs for the half year ending on 30-SEP-2006. Net Profit / (Loss) of Rs. 22314.67 lacs for the half year ending on 30-SEP-2007 against Rs. 16818.02 lacs for the half year ending on 30-SEP-2006.23 Oct · Results
Standalone Results for the quarter ended on 30-SEP-2007 as follows: Net Sales of Rs. 46638.99 lacs for quarter ending on 30-SEP-2007 against Rs. 31595.83 lacs for the quarter ending on 30-SEP-2006. Net Profit / (Loss) of Rs. 10623.35 lacs for the quarter ending on 30-SEP-2007 against Rs. 7779.51 lacs for the quarter ending on 30-SEP-2006.8 Oct · Miscellaneous
Vide their letter dated September 28, 2007 that: "The Company has commissioned its 18 MW Captive Thermal Power Plant (CPP-IV) today. The project has been setup at Bangur City, Ras, District Pali, Rajasthan".
Sep 2007
24 Sep · Miscellaneous
Vide its letter dated September 22, 2007 that "The Company has won the prestigious "Golden Peacock Award for excellence in Corporate Governance - 2007" in recognition of its best Corporate Governance practices".18 Sep · Board meeting
To consider and approve, inter-alia the Unaudited Financial Results for the Second quarter and Half Year ended on September 30, 2007.12 Sep · Meeting
Minutes of the Annual General Meeting of the Members of the Company held on August 14, 2007. A copy of the same shall be available on the NSE website (http://www.nseindia.com) under: Corporates > Latest Announcements and on the Extranet Server (/Common/Corporate Announcements). For more details click here.5 Sep · Miscellaneous
The Company has commissioned its 2.0 MTPA Cement Grinding Unit at Village Khushkhera, near Gurgaon on 3rd Sept. 2007. It has also commissioned its 1.0 MTPA Clinkerisation Unit (Unit-V) at Bangur City, Ras, District Pali, Rajasthan on 3rd Sept. 2007
Aug 2007
10 Aug · Minutes/Others
Minutes of Meeting held on July 18, 2007 for announcement of results of resolutions moved through Postal Ballot. The details of the same shall be available on the NSE website (http://www.nseindia.com) under: Corporates > Latest Announcements and on the Extranet Server (/Common/Corporate Announcements). For more details click here.
Jul 2007
25 Jul · Disclosure
Mr. M.K. Singhi, Executive Director of the Company has purchased 1500 Equity Shares of the Company on June 29, 2007. The Acquiring was through Stock Exchange. The Shareholding of Mr. M.K. Singhi before and after the above transaction is as under: 1) Shareholding before Sale of Shares - 4785; 2) % of total paid-up capital of the Company - 0.014%; 3) Shareholding after sale of shares - 6285; 4) % of total paid-up capital of the Company - 0.018%.25 Jul · Disclosure
Mr. M.K. Singhi, Executive Director of the Company has sold 500 Equity Shares of the Company on June 22, 2007. The Sale is through Stock Exchange. The Shareholding of Mr. M.K. Singhi before and after the above transaction is as under: 1) Shareholding before Sale of Shares - 5285; 2) % of total paid-up capital of the Company - 0.015%; 3) Shareholding after sale of shares - 4785; 4) % of total paid-up capital of the Company - 0.014%.21 Jul · Meeting
Register of Members and Share Transfer Books of the Company shall remain close from August 06, 2007 to August 14, 2007 (both days inclusive) for the purpose of Annual General Meeting scheduled to be held on August 14, 2007.19 Jul · Results
Standalone Results for the quarter ended on 30-JUN-2007 as follows: Net Sales of Rs. 42583.42 lacs for quarter ending on 30-JUN-2007 against Rs. 30938.62 lacs for the quarter ending on 30-JUN-2006. Net Profit / (Loss) of Rs. 11691.32 lacs for the quarter ending on 30-JUN-2007 against Rs. 9038.51 lacs for the quarter ending on 30-JUN-2006.18 Jul · Results
Special Resolution for alteration of Object Clause of Memorandum of Association of the Company has been passed by members through postal ballots with requisite majority. Declaration made by Executive Chairman of the Company in this regard shall be available on the NSE website (http://www.nseindia.com) under: Corporates > Latest Announcements and on the Extranet Server (/Common/Corporate Announcements). For more details click here.4 Jul · Board meeting
Meeting on 19 Jul 2007: “Unaudited Financial Results for the Qtr ended June 30, 2007”