- Market capMarket capitalisation. Share price times the number of shares: what the whole company is worth at the day's price. The rank is by average market value over the six months to Jun 2026, among listed companies.
- ₹1,090 Cr1,307th largest listed
- P/EPrice to earnings, trailing. Market cap divided by the profit of the last twelve months (the latest four quarters, or two half years for a company that reports half-yearly) that belongs to the company's own shareholders, after the share of the other owners of its subsidiaries: what investors pay for each rupee of a year's profit. The filing of 12 Aug 2026
- 12.8
- P/BPrice to book. Market cap divided by the net worth that belongs to the company's own shareholders, its assets less everything it owes and less the other owners' share of its subsidiaries, on its latest balance sheet.
- Shares changed
- Dividend yieldDividend yield. Dividends paid per share in the twelve months to the day, as a percentage of the day's share price.
- Nonein the last 12 months
- ROEReturn on equity. Profit over the last twelve months (the latest four quarters, or two half years for a company that reports half-yearly) that belongs to the company's own shareholders, as a percentage of their net worth, the money they have in the business. Net worth is the average of the latest balance sheet and the one a year before it. The filing of 12 Aug 2026
- 9.9%
- ROCEReturn on capital employed. Operating profit after depreciation (revenue less operating expenses and depreciation, without other income and one-off items) as a percentage of all the money the business runs on: the whole group's net worth, the other owners of its subsidiaries included, plus borrowings. Lease liabilities are not counted: the results filings do not state them. The profit is over the last twelve months (the latest four quarters, or two half years for a company that reports half-yearly); net worth and borrowings are on the latest balance sheet. The filing of 12 Aug 2026
- 6.1%
- Debt to equityDebt to equity. Borrowings divided by the whole group's net worth, the other owners of its subsidiaries included: rupees borrowed for each rupee of equity in the business. Lease liabilities are not counted: the results filings do not state them. From the balance sheet at the end of Mar 2026. The filing of 28 May 2026
- 0.37
- Volume, NSEVolume. Shares traded on the last trading day; delivery is the part buyers kept rather than sold again the same day.
- 3,55,45847.9% delivered
SPML Infra share news and announcements
814 announcements, routine notices left out, newest first. Page 17 of 17.
Jul 2007
4 Jul · Business
The Company has bagged order worth Rs.267 Crores from PHED, Jodhpur, Rajasthan for Works related to Supply of Water from Jawai & Hemawas Dams (Pali District) to Pali town and en-route Water Treatment Plants on Single Responsibility basis turnkey job contract, including necessary design and operation and maintenance4 Jul · Issue of Equity shares
The Board of Directors of the Company have, at their meeting held on June 30th 2007 and subject to the approval of the members of the Company by way of special resolution u/s 81 (1A) of the Companies Act, 1956 and subject to pricing and payment terms as per the SEBI (Disclosure & Investor Protection) Guidelines, 2000 decided to issue upto 81,63,265 Equity shares of Rs. 2/- each, at a premium of Rs. 243/- (Rupees Two Hundred Forty Three only) each, and upto 20,40,816 Warrants at an exercise price of Rs. 245/- (Rupees Two Hundred Forty Five only) of the Company, aggregating to an amount not exceeding Rs. 2,500,000,000 (Rupees Two and a Half Billion only) to : (1) CVCIGP II Client Rosehill Limited, and (2) CVCIGP II Client Employee Rosehill Limited ( the person in (a) and (b) above, collectively referred to as the Investors) on a preferential allotment basis, to the extent and in the manner approved by the shareholders of the Company. No decision or agreement has been reached by or between the investors2 Jul · Audit Qualifications
Auditors in their Report on the accounts for the year ended March 31, 2006 and March 31, 2007 had commented upon the non-provision of interest on loan to a lender due to a dispute against which an appeal is pending with the Hon'ble Court of Barasat, West Bengal and the Debt Recovery Tribunal, Delhi. As per the management, the above interest liability being presently unascertainable, would be considered in the accounts on the disposal of the legal case.2 Jul · Dividend
Board, at its meeting held on June 30, 2007 has recommended a dividend of 50% on the Equity Shares of the Company for the financial year ended March 31, 2007.
Jun 2007
28 Jun · Board meeting
Company had informed the Exchange regarding a Board Meeting Scheduled to be held on June 29, 2007, to (a) consider and approve the Audited Financial Results for the Year/Quarter ended March 31, 2007; (b) consider and recommend Dividend on the Equity Shares of the Company for the year 2006-07. The Company has now informed the Exchange that: "The next meeting of the Board of Directors of the Company will now be held on Saturday, the 30th June, 2007 instead of Friday, the 29th June, 2007 as informed earlier. Further, please note that in the meeting, the Board will also consider issuance of Equity Shares of the Company, not exceeding Rs.300 Crores to other bodies corporate on preferential basis, in accordance with the SEBI Guidelines for preferential allotment of shares". (purpose revised)21 Jun · Board meeting
To (a) consider and approve the Audited Financial Results for the Year/Quarter ended March 31, 2007; (b) consider and recommend Dividend on the Equity Shares of the Company for the year 2006-07.
May 2007
24 May · Results
Company shall publish Audited Financial Results within a period of 3 month from the Quarter ended on March 31, 2007 i.e. on or before June 30, 2007.
Apr 2007
10 Apr · Business
The Company has bagged orders cumulatively worth Rs. 309 Crores for execution of power projects. These include projects worth Rs. 220 Crores to be executed for Karnataka Power Transmission Corporation Ltd. and Hubli Electricity Supply Co. Ltd. in Karnataka and Rs. 89 Crores for Power Grid Corporation of India Ltd. (PGCIL) in Bihar on turnkey basis. The scope of work in Karnataka includes upgradation of existing sub stations, construction of 220/110/66 KV sub-stations and transmission lines. The order for PGCIL in Bihar involves construction of new underground cabling as well as revamp of existing limes under the APDRP Phase - II. The completion period for the above projects will be 12-18 months. The Company has entered the power business in 2001 and is one of the foremost players to participate in the rural electrification drive. Today, the company's power business contributes to around 50% of total order book, currently at Rs. 2900 Crores
Mar 2007
9 Mar · Limited Review Report
Auditor's have conducted the limited review of the un-audited financial results (provisional) for the quarter ended on December 31, 2006. The details of the same shall be available on the NSE website (http://www.nseindia.com) under Corporates > Latest Announcements and on the Extranet Server (/Common/Corporate Announcements). For more details click here.
Feb 2007
19 Feb · Memorandum of Understanding
The Company has entered into a Memorandum of Understanding (MOU) with the Government of Gujarat, represented by the Gujarat Urban Development Company Limited for investing in various City Development Plans of Gujarat in the following areas, namely: 1) Water Supply & Sewerage Management; 2) Solid Waste Management; 3) Electricity Utility Management; 4) Roads; 5) High Capacity Bus Services; 6) Car Parking; 7) Storm Water Drainage; 8) Real Estate Development - Township Development / Shopping Malls / Entertainment Plaza. The proposed investment of the Company is approximately Rs. 5000 Crores and the Scheme is likely to commence operation by March 2010/2012. The Governement of Gujarat will extend full support in providing basic infrastructure facilities like land, power, roads, water supply etc. and obtaining the statutory approvals for establishing and efficient running of the aforesaid projcet12 Feb · Miscellaneous
The Company has entered into Extra High Voltage (above 220KV) segment in Power projects. This will equip us to be more proficient and give us a competitive edge in the wake of upcoming opportunities in the Power sector. The Company has bagged orders worth Rs. 23 Crores from Karnataka Power Transmission Corporation Limited and Rs. 40 Crores from Haryana Vidyut Prasaran Nigam Limited. The completion period for the projects is 12 months. The scope of work for both project on partial turnkey basis includes construction of 220 KV sub station and 220 KV transmission lines, supply of all matching materials / equipments (excluding power transformer) and erection of all materials / equipments as well as testing and commissioning of the same. The Company has been focusing aggressively on the Power business since 2002. The scope of work includes mainly Transmission and Distribution (T&D) and Rural Electrification. Its current order book position is Rs. 2800 Crores1 Feb · Board meeting
(1) The Board has considered and approved formulating an Employee Stock Option Scheme (ESOS) for granting option to eligible employees of the Company and its subsidiary(ies) and has constituted a compensation Committee for the purposes of implementing, administering and supervising the ESOS in accordance with the provisions of the Securities and Exchange Board of India Employee Stock Option Scheme and Employee Stock Purchase Scheme) Guidelines, 1999. Accordingly, subject to the approval of the members of the Company, the Board has granted its approval u/s 81(1A) of the Companies Act, 1956 and other applicable provisions for granting, offering and issuing in one or more tranches, not exceeding 5% of the paid up Share Capital of the Company, i.e. not more than 15,57,820 Equity Shares of Rs. 2/- each. (2) The Board has approved, subject to the approval of members of the company and other regulatory authorities issue of securities to Qualified Institutional Buyers (QIBs), as defined under chapter XIIIA of the SEBI (Disclosure and Investor Protection) Guidelines, 2000, for an aggregate amount not exceeding USD 100 Millions or equivalent amount in Indian Rupees. (3) The Board has approved the increase in remuneration of Whole time Directors, as recommended by the Remuneration Committee of Directors
Jan 2007
25 Jan · Board meeting
Company had informed the Exchange regarding a Board Meeting scheduled to be held on January 30, 2007, to (a) consider and approve the Un-Audited Financial Results for the Quarter ended 31.12.2006; (b) consider issuance of options to employees under ESOS; (c) consider issuance of securities by way of Qualified Institutions Placement; (d) consider increase in remuneration of Whole time Directors. The company has now informed the Exchange that: "The next meeting of the Board of Directors of the Company will now be held on Wednesday, the 31st January, 2007 instead of Tuesday, the 30th January, 2007 as informed earlier".23 Jan · Board meeting
To (a) consider and approve the Un-Audited Financial Results for the Quarter ended 31.12.2006; (b) consider issuance of options to employees under ESOS; (c) consider issuance of securities by way of Qualified Institutions Placement; (d) consider increase in remuneration of Whole time Directors.