- Next results date: the board meets on 4 Nov 2026 to consider: financial results.
- Market capMarket capitalisation. Share price times the number of shares: what the whole company is worth at the day's price. The rank is by average market value over the six months to Jun 2026, among listed companies.
- ₹70,155 Cr137th largest listed
- P/EPrice to earnings, trailing. Market cap divided by the profit of the last twelve months (the latest four quarters, or two half years for a company that reports half-yearly) that belongs to the company's own shareholders, after the share of the other owners of its subsidiaries: what investors pay for each rupee of a year's profit. The filing of 4 Aug 2026
- 18.5
- P/BPrice to book. Market cap divided by the net worth that belongs to the company's own shareholders, its assets less everything it owes and less the other owners' share of its subsidiaries, on its latest balance sheet. The filing of 15 May 2026
- 1.7
- Dividend yieldDividend yield. Dividends paid per share in the twelve months to the day, as a percentage of the day's share price.
- 2.31%
- ROEReturn on equity. Profit over the last twelve months (the latest four quarters, or two half years for a company that reports half-yearly) that belongs to the company's own shareholders, as a percentage of their net worth, the money they have in the business. Net worth is the average of the latest balance sheet and the one a year before it. The filing of 4 Aug 2026
- 9.4%
- ROCEReturn on capital employed. Operating profit after depreciation (revenue less operating expenses and depreciation, without other income and one-off items) as a percentage of all the money the business runs on: the whole group's net worth, the other owners of its subsidiaries included, plus borrowings. Lease liabilities are not counted: the results filings do not state them. The profit is over the last twelve months (the latest four quarters, or two half years for a company that reports half-yearly); net worth and borrowings are on the latest balance sheet. The filing of 4 Aug 2026
- 3.6%
- Debt to equityDebt to equity. Borrowings divided by the whole group's net worth, the other owners of its subsidiaries included: rupees borrowed for each rupee of equity in the business. Lease liabilities are not counted: the results filings do not state them. From the balance sheet at the end of Mar 2026. The filing of 15 May 2026
- 1.08
- Volume, NSEVolume. Shares traded on the last trading day; delivery is the part buyers kept rather than sold again the same day.
- 1,36,59,03751.9% delivered
NHPC share news and announcements
1,236 announcements, routine notices left out, newest first. Page 22 of 25.
Sep 2014
Aug 2014
21 Aug · Meeting
Annual General Meeting of the members of the Company is scheduled to be held on September 26, 2014. The Register of Members and Share Transfer Books of the Company shall remain closed from September 13, 2014 to September 26 , 2014 (both days inclusive) for the purpose of determination of entitlement to receive dividend if approved at the AGM.
Jul 2014
24 Jul · Meeting
22 Jul · Board meeting
To consider the financial results of the Company for the quarter ended June 30, 2014.8 Jul · Dividend
Board of Directors at its meeting held on July 07, 2014 has recommended a final dividend @3% (Rs 0.30 per equity share) on the paid up share capital of the Company for the financial year 2013-2014.Final Dividend, if approved and declared in the Annual General Meeting, shall be paid/dispatched within the period as stipulated in Companies Act, 2013.
Jun 2014
5 Jun · Updates
Consequent upon successful trial run of unit# 4 of Parbati-III power station (4x130 MW) at its maximum continuous rating of 130 MW for 12 hours on June 03, 2014, unit # 4 is hereby declared under commercial operation w.e.f 00:00 hrs of June 06, 2014.
May 2014
31 May · Board meeting
Board of Directors of the Company at its meeting held on May 30, 2014, has not taken any decision about recommendations on dividend.27 May · Board meeting
Company had informed the Exchange that the Board of Directors of the Company will consider the results of the Company for the year ended March 31, 2014 in its meeting scheduled to be held on May 27, 2014 for approval and submission to auditors for their report and to recommend dividend, if any for the year 2013-14. The Company has now informed the Exchange that the aforesaid Board Meeting shall now be held on May 30, 2014.12 May · Updates
An agreement was signed between NHPC Limited and Kerala State Electricity Board on May 08, 2014 at Thiruvanthapuram for the development of Solar Power Projects in the state of Kerala. As per this agreement NHPC shall in the first phase take up implementation of 50 MW grid linked solar power project at West Kallada Panchayat in Kollam District.
Mar 2014
28 Mar · Updates
Ministry of Power vide its order dated March 24, 2014 has extended the tenure of Shri D. P. Bhargava, Director (Technical) and Shri R. S. Mina, Director (Personnel) for a period of three months beyond the date of completion of their tenure of five years in NHPC Ltd i.e. March 25, 2014 and April 27, 2014 respectively or until further orders, whichever is earlier.18 Mar · Updates
Unit-Ill of Parbati H.E. Project has been synchronized with grid on March 15, 2014 at 00.34 hours and commissioned at full load (130 MW) successfully on March 15, 2014 at 15.30 hours.4 Mar · Corporate action
First interest on payment on Secured,Redeemable, Non-cumulative Tax Free bonds Series '1A', '1B', '2A', '2B;'3A' and '3B' is due on April 01, 2014. The Company has fixed March 14, 2014 as record date for the purpose of payment of interest of Tax free Bonds (ISIN- INE848E07518, INE848E07526, INE848E07534, INE848E07542, INE848E07559 & INE848E07567).3 Mar · Updates
Unit-2 of Parbati-III H.E. Project has been synchronized with grid at 06:22 hours on February 27, 2014.
Feb 2014
28 Feb · Updates
Consequent upon successful trial run of unit # 4 of Uri - II HE Project (4 X 60 MW), the project is declared under commercial operation w.e.f. 00:00 hrs of March 03, 2014. The Unit # 1 & 3 and Unit # 2 of the project are already under commercial operation w.e.f 00:00 hrs of October 11, 2013 and 00.00 hrs of December 01, 2013 respectively .24 Feb · Updates
An MoU has been signed on February 22, 2014 amongst NHPC Limited, Bihar State Power Generation Company Limited and Pirpainti Bijlee Company Pvt Limited (PBCPL) for participation in PBCPL, to develop 1320 (2X660) MW Pirpainti Supercritical Thermal Power Project in Distt Bhagalpur of Bihar state.18 Feb · Updates
Unit-1 of Parbati-III H.E. Project has been synchronized at 3:50 hours on February 17, 2014.4 Feb · Updates
Unit-4 of Uri-ll H.E. Project was synchronized with full load on February 02, 2014 at 7:20 P.M. Now all the four units of 60 MW each stand commissioned.
Jan 2014
14 Jan · Board meeting
To consider the financial results of the Company for the quarter ended December 31, 2013.8 Jan · Updates
An MoU has been signed on January 06, 2014 between Company and Government of Kerala for the development of Wind Power project by NHPC in Kerala. As per the agreement NHPC shall take up the grid interactive wind energy project with proposed installed capacity of 82MW in Palakkad District of Kerala.
Dec 2013
23 Dec · Updates
Promoters' Agreement has been signed on December 21, 2013 between NHPC Limited, Government of Odisha and Odisha Hydro Power Corporation Limited for formation of a Joint Venture Company for implementation of six hydroelectric projects with an aggregate Installed capacity of 1020 MW.
Nov 2013
22 Nov · Buyback
Date of opening of the Buyback Offer is November 29, 2013 and the date of closing of the Buyback Offer is December 12, 2013.18 Nov · Updates
Third unit (Unit No 2) of Uri-ll HE Project has been successfully commissioned with effect from 1619 Hrs on November 16, 2013.11 Nov · Management
Ministry of Power vide its letter November 04, 2013 has appointed Shri Mukesh Jain, Joint Secretary (H) Ministry Of Power, as part time Government Director on the Board of the Company.
Oct 2013
29 Oct · Public Announcement - Buyback of Shares
28 Oct · Board meeting
To consider the financial results of the Company for the quarter/half year ended September 30, 2013.28 Oct · Corporate action
Functional Authority, duly constituted by the Board, has fixed November 08, 2013 as Record Date for the purpose of determination of eligible shareholders for Buyback of Equity Shares of NHPC Limited.28 Oct · Public Announcement - Buyback of Shares
24 Oct · Buyback
Board of directors of the Company at its meeting held on October 24,2013 has unanimously approved the Buy-back of upto 10% of fully paid up equity shares of Rs.10 each at Rs.19.25 per share payable in cash for an aggregate amount of Rs.23,67,89,29,832 (Rupees Two Thousand Three Hundred Sixty Seven Crore Eighty Nine Lacs Twenty Nine Thousand Eight Hundred Thirty Two only) through tender offer.21 Oct · Board meeting
To be consider a proposal for Buy-Back of Equity Shares.14 Oct · Updates
Consequent upon successful commissioning of Unit # 1, Unit # 2 and Unit # 3 of Nimoo Bazgo HE Project (3x15MW) to the extent of maximum load provided by PDD J&K, Commercial Operation of these units and the station has been declared w.e.f. 00.00 hrs of October 10, 2013.