Mcnally Bharat Engineering Company share news and announcements
NSE: MBECLBSE: 532629ConstructionSmall Cap
Share price at the NSE close on 23 Oct 2026. Previous close ₹395.65.
- Delivery only: shares bought must be paid for in full, with no selling on the same day.
- Market capMarket capitalisation. Share price times the number of shares: what the whole company is worth at the day's price. The rank is by average market value over the six months to Jun 2026, among listed companies.
- ₹1,293 Cr3,340th largest listed
- P/EPrice to earnings, trailing. Market cap divided by the profit of the last twelve months (the latest four quarters, or two half years for a company that reports half-yearly) that belongs to the company's own shareholders, after the share of the other owners of its subsidiaries: what investors pay for each rupee of a year's profit. The filing of 12 Aug 2026
- 0.4
- P/E without one-offsPrice to earnings without one-off items. Market cap divided by core profit: the profit of the last twelve months (the latest four quarters, or two half years for a company that reports half-yearly) that belongs to the company's own shareholders, less one-off items (exceptional items and the result of businesses sold or closed). Shown where the one-off items move that profit by more than a tenth. The last twelve months' profit includes ₹3,876 crore of one-off items, the largest of them in the quarter to Sep 2025.
- Lossover the last 12 months
- P/BPrice to book. Market cap divided by the net worth that belongs to the company's own shareholders, its assets less everything it owes and less the other owners' share of its subsidiaries, on its latest balance sheet. The filing of 28 May 2026
- 2.3
- Dividend yieldDividend yield. Dividends paid per share in the twelve months to the day, as a percentage of the day's share price.
- Nonein the last 12 months
- ROEReturn on equity. Profit over the last twelve months (the latest four quarters, or two half years for a company that reports half-yearly) that belongs to the company's own shareholders, as a percentage of their net worth, the money they have in the business. Net worth is the latest balance sheet's; the one a year before is not on record. The filing of 12 Aug 2026
- 640.3%
- ROE without one-offsReturn on equity without one-off items. Core profit, the profit of the last twelve months (the latest four quarters, or two half years for a company that reports half-yearly) that belongs to the company's own shareholders less one-off items (exceptional items and the result of businesses sold or closed), as a percentage of the same net worth as the return on equity. Shown where the one-off items move that profit by more than a tenth. The last twelve months' profit includes ₹3,876 crore of one-off items, the largest of them in the quarter to Sep 2025.
- −38.8%
- ROCEReturn on capital employed. Operating profit after depreciation (revenue less operating expenses and depreciation, without other income and one-off items) as a percentage of all the money the business runs on: the whole group's net worth, the other owners of its subsidiaries included, plus borrowings. Lease liabilities are not counted: the results filings do not state them. The profit is over the last twelve months (the latest four quarters, or two half years for a company that reports half-yearly); net worth and borrowings are on the latest balance sheet. The filing of 12 Aug 2026
- −31.9%
- Debt to equityDebt to equity. Borrowings divided by the whole group's net worth, the other owners of its subsidiaries included: rupees borrowed for each rupee of equity in the business. Lease liabilities are not counted: the results filings do not state them. From the balance sheet at the end of Mar 2026. The filing of 28 May 2026
- 0.17
- Volume, NSEVolume. Shares traded on the last trading day.
- 11
Mcnally Bharat Engineering Company share news and announcements
1,054 announcements, routine notices left out, newest first. Page 20 of 22.
Jan 2010
13 Jan · Board meeting
Meeting on 29 Jan 2010: “Unaudited Financial Results for the qtr ended Dec 31, 2009”
Dec 2009
24 Dec · Meeting
Minutes of the Annual General Meeting of the members of the Company held on November 23, 2009. A copy of the same shall be available on the NSE website (http://www.nseindia.com) under: Corporates > Latest Announcements and on the Extranet Server (/Common/Corporate Announcements). For more details click here.24 Dec · Limited Review/Others
Auditors have conducted the limited review for the un-audited financial results for the quarter ended September 30,2009 A copy of the same shall be available on the NSE website (http://www.nseindia.com) under: Corporates > Latest Announcements and on the Extranet Server (/Common/Corporate Announcements). For more details click here.15 Dec · Updates
Shareholders at the Annual General Meeting held on November 23, 2009 adopted a resolution for issue of Rights Shares at the ratio of 1 new share for every 10 shares held at a premium of Rs.130 that is Rs.140 in all. A certified copy of the resolution shall be available on the NSE website (http://www.nseindia.com) under Corporates > Latest Announcements and on the Extranet Server (/Common/Corporate Announcements). For more details click here.
Nov 2009
23 Nov · Management
"The Board of Directors at their meeting held on 23rd November, 2009 has appointed Mr. Asim Barman, IAS (Retirsd) as an Independent Director with effect from 1st December, 2009". The details of the same shall be available on the NSE website (http://www.nseindia.com) under: Corporates > Latest Announcements and on the Extranet Server (/Common/Corporate Announcements). For more details click here.23 Nov · Meeting
Outcome of Annual General Meeting held on November 23, 2009. The details of the same shall be available on the NSE website (http://www.nseindia.com) under: Corporates > Latest Announcements and on the Extranet Server (/Common/Corporate Announcements). For more details click here.19 Nov · Updates
We have received an order for Design, Engineering, Manufacture, Supply, Erection, Commissioning and Performances Guarantee of New Coal Handling Plant in Coke Oven Battery#6 Area (Pkg No. 091) at Rourkela Steel Plant, Rourkela for a value of Rs. 306.45 crores. The contractual period of completion is 24 months16 Nov · Sale of shares
We have received an intimation from Mr. Dibakar Chatterjee, Company Secretary declaring that he has sold his entire shareholding of 1000 Equity Shares of the Company on 9 November, 2009 in Open Market through Bombay Stock Exchange
Oct 2009
22 Oct · Disclosure
Company have sold 1,48,598 equity shares of Rs.10/- each fully paid up of McNally Sayaji Engineering Limited to EIG (Mauritius) Limited on 20.10.2009. With this sale, Company's holding in McNally Sayaji Engineering Limited have decreased from 64,78,296 (88.07% of issued capital) Equity shares to 63,29,698 Equity shares (86.05%) of issued capital). The details of the same shall be available on the NSE website (http://www.nseindia.com) under: Corporates > Latest Announcements and on the Extranet Server (/Common/Corporate Announcements). For more details click here.16 Oct · Meeting
Annual General Meeting of the Company will be held on November 23, 2009. The Register of Members and Share Transfer Books of the Company will remain closed from 16th to 23rd November, 2009 for the purpose and for payment of Dividend, if approved in the aforesaid AGM. Further, the Company has informed that the Registrar of Companies, West Bengal have granted time extension of 3 months for holding the AGM by virtue of Section 166 (1) vide letter dated September 10, 2009.16 Oct · Board meeting
Meeting on 31 Oct 2009: “Unaudited Financial Results for the Qtr ended Sept 30, 2009”
Sep 2009
7 Sep · Dividend
Board of Directors at their meeting held on September 07, 2009 has: (a) Recommended a dividend of 12.5% (i.e. Rs.1.25 per Share) for the year ended March 31, 2009 subject to the approval of the members. (b) Recommend fresh issue of equity shares on rights basis subject to the approval of the members to rank pari passu with the existing shares in the ratio of one new equity share for every ten equity shares held in the Company at Rs 140 per share fully paid up that is Rs 10 per share at a premium of Rs 130.4 Sep · Limited Review Report
Auditors have conducted the limited review for the un-audited financial results for the quarter ended June 30,2009. A copy of the same shall be available on the NSE website (http://www.nseindia.com) under: Corporates > Latest Announcements and on the Extranet Server (/Common/Corporate Announcements). For more details click here.
Aug 2009
31 Aug · Board meeting
To consider the following (1) To take on record the Audited Financial Result of the Company for the year ended March 31, 2009 and (2) To recommend Dividend, if any28 Aug · Receipt of Order
We have received an order for Supply and Installation of Water Pre-Treatment Plant Package for Rihand Super Thermal Power Project, Stage II (2X 660MW) for NTPC Ltd for a value of Rs. 24.69 crores. The contractual period of completion is 28 months27 Aug · Receipt of Order
Company have received the following orders from HINDALCO Industries Limited: (1) An order for Design, Engineering, Supply, Erection, Testing and Commissioning including Civil works and Structural works at site for Green Anode Plant of Aditya Alumina Project (52 TPH) at Orissa for a value of Rs. 86.66 Crores. (2) An order for Design, Engineering, Supply, Erection, Testing and Commissioning including Civil works and Structural works at site for Green Anode Plant of Mahan Alumina Project (35 TPH) at Madhya Pradesh for a value of Rs. 92.61 Crores.21 Aug · Updates
McNally Bharat Engineering Co Ltd (MBE) announces that its wholly owned Singapore subsidiary, MBE Holdings Pte Ltd, on August 20, 2009 has entered into purchase agreements for the acquisition of KHD Humboldt Wedag's world wide coal and minerals business and its manufacturing facility in Cologne. Closing is subject to customary conditions.17 Aug · Receipt of Order
We have received an Order from Bharat Heavy Electricals Ltd, Chennai for design, engineering, erection & commissioning of Coal Handling Plant for 1 x 500 MW TPS Stage - 2 at Bellary for a total value of Rs. 151.50 Crores (including taxes and duties)13 Aug · Updates
"We have sold 3,83,058 equity shares of Rs. 10/- each fully paid up of McNally Sayaji Engg. Ltd (MSEL) to EIG (Mauritius) Limited on 12.08.2009. With this sale, our holdings in McNally Sayaji Engg. Ltd have decreased from 34,05,825 equity shares to 30,22,767 equity shares i.e. from 87.32% to 77.50% of the issued capital of the Company". Further the Company has submitted to the Exchange a copy of Form C required by SEBI (Prohibition of Insider Trading) Regulations, 1992. A copy of the same shall be available on the NSE website (http://www.nseindia.com) under: Corporates > Latest Announcements and on the Extranet Server (/Common/Corporate Announcements). For more details click here.
Jul 2009
31 Jul · Receipt of Order
We have received an order for Design, Engineering, Manufacturing, Supply, Erection, Testing and Commissioning of Balance of Plant on EPC basis including Civil works for 1X270 MW Coal based Power Project of Ideal Energy Projects Limited (IEPL) near village Bela at Nagpur, Maharashtra for a value of Rs. 414 crores including taxes and duties15 Jul · Board meeting
Meeting on 31 Jul 2009: “Unaudited Financial Results for the Qtr ended June 30, 2009”10 Jul · Receipt of Order
We have received 2 orders for Design, Enginnering, Manufacturing, Testing, Erection and Commissioning of Ash Handling Systems for 2X600 MW Mahan and Salaya Essar Power Projects for Rs. 69 crores and Rs. 24 Crores respectively. The contractual period of completion for Mahan Essar Power Projects is 16 months and for Salaya Essar Power Project is 14 months7 Jul · Receipt of Order
We have received an order for Design, Engineering, Manufacturing and Supply, Erection and Commissioning of Stock House Package for Rourkela Steel Plant (Package No. 10) for Tata Project Limited for a value of Rs. 165 crores including taxes and duties. The contractual period of completion is 20 months2 Jul · Receipt of Order
We have received the following orders: 1) Order for Ex-works Supply of Pre-Treatment Plant Package for Mauda Super Thermal Power Project (2X500 MW) for NTPC Ltd in Noida, U.P. for a value of Rs. 15.44 crores including taxes and duties. The contractual period of completion of the order is 28 months. 2) Order for Supply and Installation of Water- Pre-Treatment Plant Package for Barh Super Thermal Power Project, Stage- II (2X660 MW) for NTPC Ltd in Noida, U.P. for a value of Rs. 31.44 crores including taxes and duties. The contractual period of completion of the order is 42 months1 Jul · Receipt of Order
Company has received an order for Supply and Installation for Ash handling Package of 3X250 MW NTPC Bangaigaon TPP for a value of Rs. 81.93 crores including taxes and duties. The contractual period of completion is 31 months.
Jun 2009
22 Jun · Receipt of Order
Company has received an order for Design, Manufacture, Supply, Installation and Commissioning of 02 Nos. 3000 TPH capacity Reclaimers at Paradip, Dist: Jagatsinghpur, Orissa from Paradip Port trust for a value of Rs. 30.60 crores including taxes and duties.12 Jun · Updates
Company has received an order for a 2.0 MTPA Pb-Zinc Beneficiation Plant at Sindesar Khurd Mines, Rajasthan from Hindustan Zinc Limited (HZL) for a value of Rs. 300 Crores including taxes and duties. The contractual period for completion of the order is 18 months.1 Jun · Limited Review Report
Auditors have conducted the limited review for the un-audited financial results for the quarter ended March 31, 2009. The reply to the Comments of the Auditors Report given by the Company and the details of the Limited Review Report shall be available on the NSE website (http://www.nseindia.com) under: Corporates > Latest Announcements and on the Extranet Server (/Common/Corporate Announcements). For more details click here.
May 2009
6 May · Memorandum of Understanding
Company has signed a MOU with KHD Humboldt Wedag International GMBH and its subsidiaries in Germany, India and in Hong Kong to buy their engineering workshop in Cologne, Germany and their CMT (Coal and mineral technology) business based in Germany, India, South Africa, Russia and China having a turnover of around US$ 50 Million. The details of the same shall be available on the NSE website (http://www.nseindia.com) under: Corporates > Latest Announcements and on the Extranet Server (/Common/Corporate Announcements). For more details click here.
Apr 2009
23 Apr · Board meeting
To inter-alia consider and take on record the Unaudited Financial Results of the Company for the quarter and year ended March 31, 2009.
Mar 2009
2 Mar · Updates
Steel Authority of India Ltd, IISCO Steel Plant, Burnpur, West Bengal has accepted our offer for Water Supply System for CCP & BOF for a total price of Rs.115.92 crores inclusive of tax and duties. The time of completion shall be 18 months from the Effective Date of Contract2 Mar · Updates
Our ASANSOL PLANT at Kanyapur Industrial Area in West Bengal has been put to use with effect from March 01, 2009 and Commercial Production has started
Feb 2009
25 Feb · Limited Review Report
Auditors have conducted the limited review for the un-audited financial results for the quarter ended December 31,2008.A copy of the same shall be available on the NSE website (http://www.nseindia.com) under: Corporates > Latest Announcements and on the Extranet Server (/Common/Corporate Announcements). For more details click here.13 Feb · Disclosure
Disclosure pursuant to Regulation 8A(4) of the SEBI (Substantial Acquisition of Shares and Takeovers) Regulations, 1997 as amended by (Amendment) Regulations, 2009. The details of the same shall be available on the NSE website (http://www.nseindia.com) under: Corporates > Latest Announcements and on the Extranet Server (/Common/Corporate Announcements). For more details click here.3 Feb · Outcome of Court Convened Meeting
Equity Shareholders of the Company at its meeting held on February 02, 2009 in pursuance of the Order of the High Court at Calcutta dated December 22, 2008 have passed the following resolution by majority : "Resolved that the Scheme of Arrangement proposed to be made between McNally Bharat Engineering Company Limited and McNally Sayaji Engineering Limited and their respective Shareholders, being Annexure "A" in Company Application no. 720 of 2008, a copy whereof is included in the notice dated the 7th day of January, 2009 convening this Meeting, be and is hereby approved".
Jan 2009
30 Jan · Updates
Information update of the Company for the period ended December 31, 2008. A copy of the same shall be available on the NSE website (http://www.nseindia.com) under: Corporates > Latest Announcements and on the Extranet Server (/Common/Corporate Announcements). For more details click here.22 Jan · Notice of Meeting
By an order made on December 22, 2008 the Hon'ble High Court at Calcutta has directed that a meeting of the Equity Shareholders of McNally Bharat Engineering Company Limited, being the Applicant Company (hereinafter referred to as "MBECL") be held on February 02, 2009 for the purpose of considering and if thought fit, approving, with or without modification, the Scheme of Arrangement proposed to be made between MBECL and McNally Sayaji Engineering Limited and their respective Shareholders. A copy of the notice of meeting shall be available on the NSE website (http://www.nseindia.com) under: Corporates > Latest Announcements and on the Extranet Server (/Common/Corporate Announcements). For more details click here.19 Jan · Board meeting
Meeting on 30 Jan 2009: “Unaudited Financial Results for the qtr ended Dec 31, 2008”
Dec 2008
18 Dec · Updates
Company has received 2 orders from Vedanta Group for 1.5 million tones per annum capacity Lead Zinc Beneficiation plant for Rampura Agucha Mines, Bhilwara (Rajasthan) and 1 Aluminium Handling package at Lanjigarh, Orissa for a total value of Rs. 244 Crores (including taxes and duties).15 Dec · Updates
Company has received orders from Essar Constructions (India) Ltd., Mumbai for supply of the following material for their different plants for a total value of Rs.86.66 crores inclusive of taxes: (1) Slewable Boom Stacer for Beneficiation Plant a Dabuna, Orissa. (2) Slewable Boom Stacker & Bucket Wheel Relaimer for Paradeep Plant in Orissa. (3) 3 nos. Stacker cum Reclaimer for Salaya Thermal Power Plant Project. (4) 2 nos. Stacker cum Reclaimer for Mahan thermal Power Plant Project.2 Dec · Limited Review Report
Auditor's have conducted the limited review of the unaudited financial results for the quarter ended September 30, 2008 along with the Company's reply to the Comments of the Auditors Report. A copy of the same shall be available on the NSE website (http://www.nseindia.com) under: Corporates > Latest Announcements and on the Extranet Server (/Common/Corporate Announcements). For more details click here.
Nov 2008
10 Nov · Business
Vide its letter dated November 10, 2008 that "The Board of Directors of McNally Bharat Engineering Company Limited (MBECL) at their meeting held have today approved of a Scheme of Arrangement for Reconstruction of MBECL and its subsidiary, namely McNally Sayaji Engineering Limited (MSEL), whereby and whereunder the Products Division of MBECL engaged in the business of manufacturing and/or procuring equipment for various engineering and infrastructure projects, having its units at (i) Kumardhubi in the State of Jharkhand, (ii) Asansol in the State of West Bengal and (iii) Bangalore in the State of Karnataka will be transferred to MSEL with effect from the Appointed Date i.e. April 1, 2008. The rest of the business and undertaking of MBECL will continue to remain with MBECL. The Scheme is subject to and conditional upon the requisite approvals being received therefore, including approval of shareholders and sanction of the Hon'ble High Court(s) pursuant to Sections 391 to 394 of the Companies Act, 1956. Accordingly, the Scheme although operative from the Appointed Date shall come into effect on the Effective Date, being the date or last of the dates on which certified copies of the orders sanctioning the Scheme are filed by MBECL and MSEL with the Registrar of Companies. In consideration of transfer of the Products Division, MSEL will issue and allot to MBECL, 34.55 Lakhs Equity Shares of Rs.10/- each, credited as fully paid up in MSEL. The shareholding of MBECL in MSEL will increase accordingly and MSEL will continue to be a subsidiary of MBECL".3 Nov · Board meeting
To consider, inter alia, a Scheme of Arrangement for Reconstruction of the Company and its subsidiary, namely, Sayaji Iron & Engineering Company Limited, by transfer of the Product Division of the Company to the said subsidiary pursuant to the provisions of Sections 391 and 394 of the Companies Act, 1956.
Oct 2008
31 Oct · Updates
Vide its letter dated October 31, 2008 that, "The Board of Directors of the Company at their meeting held today also resolved to consider proposed Reconstruction of the Company and its subsidiary, namely, Sayaji Iron & Engineering Company Limited, by transfer of the Product Division of the Company to the said subsidiary pursuant to the provisions of Section 391 and 394 of the Companies Act, 1956, upon development and formulation of the proposal, including terms and conditions thereof, in consultation with legal advisers and valuers."13 Oct · Board meeting
Meeting on 31 Oct 2008: “Unaudited financial results for qtr ended September 30, 2008”6 Oct · Meeting
Minutes of Proceedings of the Annual General Meeting of the Company held on September 15, 2008. A copy of the same shall be available on the NSE website (http://www.nseindia.com) under: Corporates > Latest Announcements and on the Extranet Server (/Common/Corporate Announcements). For more details click here.
Sep 2008
26 Sep · Updates
We have received an Order from Bharat Heavy Electricals Ltd, Bangalore, for Design, Engineering, Supply, E&C and Structural Steel Works of Coal Handling Plant Mechanical Equipments for GSECL, 1x500 MW UKAI Project valued at Rs. 115 crores inclusive of all taxes and duties. The completion shall be 18 months from the date of LOI17 Sep · Updates
We have received an Order from Damodar Valley Corporation for design, engineering, supply, erection, testing and commissioning a combined ash slurry disposal system for both coal based Bokaro TPS 'A' 1x(500 MW + 20%) and 'B' (3x210 MW) valued at Rs. 87.12 crores inclusive of all taxes and duties15 Sep · Meeting
Outcome of Annual General Meeting of the Company held on September 15, 2008. The details of the same shall be available on the NSE website (http://www.nseindia.com) under: Corporates > Latest Announcements and on the Extranet Server (/Common/Corporate Announcements). For more details click here.8 Sep · Limited Review Report & Others
Auditor's have conducted the limited review of the unaudited financial results for the quarter ended June 30, 2008 along with the Company's reply to the Comments of the Auditors Report. A copy of the same shall be available on the NSE website (http://www.nseindia.com) under: Corporates > Latest Announcements and on the Extranet Server (/Common/Corporate Announcements). For more details click here.